Solar Installer Instructions
Instructions for Installing a Solar System in Burbank
The rules and guidelines for installing solar varies by city. The following steps will provide you with a complete guideline to installing a solar system at a home or business in Burbank.
Step 1: Get Confirmation of Services Document
Please download the instructions and details for receiving the Confirmation of Electric Service document. You'll need to submit this document and a full set of plans to the Burbank Building Division.
Step 2: Electrical Interconnection & Metering Agreement
Download and complete two signed original copies of the Interconnection and Net Metering Agreement. Email the completed documents to BWP Service Planning: [email protected]. BWP staff will reply with a meter spot and confirmation number to use when applying for a permit.
Step 3: Apply for a Permit
A building permit is required for the installation of any solar system in Burbank. Permits are handled through the City of Burbank Building Division.
Residential PV Systems
Once you have obtained your BWP meter spot and confirmation number from Step 2, please navigate to the City of Burbank Building Division to begin your instant solar permit application. You should have your meter spot available to upload and reference in your application. Please contact BWP Residential Service Planning (link to [email protected]) if you experience any technical issues with your BWP confirmation number.
Commercial PV Systems
Require a Tier 2 permit application with a plan check: Once you have obtained your BWP meter spot, please contact the Building and Safety Division via email at [email protected] for access to the online review portal named Projectdox. For additional information about Tier 2 permits and Projectdox go to the Building Permits page.
Step 5: Install the Solar System!
Pay close attention to labeling requirements for solar equipment to avoid additional inspection costs and a delay in installation completion. For labeling questions contact BWP’s Test Shop M-F 7:00 am to 4:00 pm at (818) 238-3585.
Step 6: Schedule Inspections & Finalize Permit
Now that the solar system installation is complete, you will need to schedule your inspection one day in advance. Set up or login to the Burbank Online Permits portal and schedule an inspection. For questions, the Building Division can be reached by email: [email protected].
Step 7: BWP Installs the Performance Meter
When the building inspection has been completed, BWP will be notified by the Building Division Inspector. BWP will provide and schedule an on-site field visit to install the performance meter and perform various safety tests on your solar system.